Street Closings and Restrictions

Street Closings and Restrictions

CITY OF INDIANAPOLIS STREET CLOSINGS  AND TRAFFIC RESTRICTIONS

May 16, 2008

***Asterisks indicate new or updated information***

 NEW OR UPDATED RESTRICTIONS
(INDOT Projects )

 The following restrictions are current or upcoming for the Indianapolis metropolitan region. Many restrictions listed below are dependent upon favorable weather conditions.

SIGNIFICANT "PROJECT OPEN MARKET" TRAFFIC CHANGES BEGIN

INDIANAPOLIS - Beginning Monday, May 19, 2008, the Indianapolis Department of Public Works (DPW) will close College Avenue (one-way northbound) to through traffic between Fletcher Avenue and Washington Street. As part of Project Open Market, this closure will last 24 hours a day, for approximately two weeks, while storm sewer construction work is conducted at the intersection of Washington Street and College Avenue.

Washington Street will also be reduced to four lanes (two eastbound and two westbound) 24 hours a day from College Avenue to Davidson Street during this two-week time period.

Other lane restrictions and traffic changes are expected throughout the summer as work on Project Open Market progresses east of College Avenue along Washington Street. DPW encourages residents and motorists to visit www.indygov.org/dpw/openmarket to sign up for e-mail traffic alerts.

DETOUR ROUTES

Drivers affected by the College Avenue closure should take:
 
• South Street (Fletcher Avenue) west to Delaware Street, Delaware Street north to New York Street, New York Street east to College Avenue

Drivers affected by the Washington Street lane restrictions should take:

• State Avenue north to Michigan Street, west on Michigan Street (westbound traffic)
• East on New York Street, south on State Street (eastbound traffic)

PROJECT OPEN MARKET

Project Open Market is a city initiative to spur investment and create economic opportunity on the Near-Eastside by removing the Market Street I-65/70 interstate ramp and building a new interchange along East Washington Street. The project, financed mostly through federal grant dollars, will open up Market Street for new business opportunities and create a more pedestrian-friendly corridor that will better connect the Near-Eastside to downtown Indianapolis. For more information, visit: www.indygov.org/dpw/openmarket.

Work to Begin on I-465 Interchange

Left turn closures planned at I-465 SB ramps with Pendleton Pike 

INDIANAPOLIS – Starting next week, left turn movements will be restricted at the I-465 southbound ramps with U.S. 36/Pendleton Pike. AT&T will be splicing new lines underneath the roadway that will require about two weeks of lane closures around their manholes. AT&T plans to have day and night crews working to complete the complex connections. 

No later than the morning of Monday, May 19, traffic exiting I-465 southbound will not be able to turn left onto eastbound U.S. 36/S.R. 67 (Pendleton Pike). Westbound Pendleton Pike traffic will also be unable to turn left onto the ramp entering I-465 southbound. Large orange construction signs along I-465 and Pendleton Pike encourage through traffic to use East 56th Street as an alternate route around construction. The Indiana Department of Transportation anticipates the left turn restrictions will be lifted in early June.


The entrance and exit ramps that connect I-465 northbound with Rockville Road are scheduled to reopen before the Indianapolis 500 and the busy Memorial Day travel weekend. Motorists and commuters should anticipate construction delays and begin planning alternate routes. Posted detours will direct traffic to the nearby West 10th Street and Washington Street interchanges. During these few weeks, all entrance and exit ramps connecting I-465 southbound with Rockville Road will remain open. 

INDOT also plans traffic flow improvements to ten busy intersections on the Westside for motorists seeking alternate routes. As early as Monday, May 5, road crews will begin work at two intersections, Rockville Road at Lynhurst Drive and Rockville Road at Washington Street. Road crews will build new or extended turn lanes at each intersection to prevent motorists turning left or right from blocking through traffic. Other intersections slated for improvement, in order, include: 

  • Kentucky Avenue and Lynhurst Drive
  • Rockville Road and Girls School Road
  • Rockville Road and Holt Road
  • Girls School Road and West 10th Street
  • Crawfordsville Road and Dandy Trail
  • West 21st Street and Cunningham Road
  • West 26th Street and Moller Road
  • Washington Street and Girls School Road  

As one of the first segments of I-465 ever built, the eleven miles of interstate between West 56th Street and S.R. 67/Kentucky Avenue cannot handle existing traffic volumes at peak periods. Accelerate 465 is a Major Moves corridor project that will add lanes to I-465 and reconfigure interchanges to promote the free-flow movement of traffic. Pedestrian crossings, noise barriers and other improvements will benefit nearby residents.  

Gov. Mitch Daniels' Major Moves highway program capitalizes on Indiana's strategic location at the Crossroads of America by building a superior road infrastructure. When complete in 2015, nearly $12 billion in critical highway projects will have been built. This innovative plan will bring jobs to the Hoosier State and leave a legacy for Indiana to be a global leader in distribution and logistics.

In the next 30 to 60 days, the town will widen Dan Jones Road from about 10 feet to 12 feet from County Road 100 South to 200 South.
For more information visit www.co.hendricks.in.us

INDIANAPOLIS – The following restrictions are current or upcoming for the Indianapolis metropolitan area. Many restrictions listed below are dependent upon favorable weather conditions.

 NEW RESTRICTIONS 

·         I-465 and I-70, on the city's southwest side, will encounter nighttime lane closures for installation of temporary airport signage.

.         I-70 in both directions between Harding Street and S.R. 267

.         I-465 in both directions between S.R. 37/Harding Street and U.S. 36/Rockville Road

Date: Wednesday, April 30 – Friday, May 30, 2006
Time: 7 p.m. – 5 a.m.
 

·        I-465 northbound entrance and exit ramps at Rockville Road will be closed as part of traffic preparations for Accelerate 465 interchange reconstruction. All entrance and exit ramps connecting I-465 southbound with Rockville Road will remain open at this time.
Date: Saturday, May 3 – Friday, May 23, 2008
Time: Continuous
 
·         Rockville Road intersections with Lynhurst Drive and Washington Street may encounter lane restrictions while crews perform intersection and signal improvements.
Date: Monday, May 5 – Friday, May 23, 2008
Time: 9 a.m. – 4 p.m.

 ·         I-65/I-70 southbound exit to Fletcher Avenue will encounter a new traffic pattern for ramp reconstruction. Traffic will be shifted from the left side of the ramp to the right side as part of an Indianapolis DPW project to reconfigure interstate access in the area. Click here for more Project Open Market information 
Date: Friday, April 18 – May 2008
Time: Continuous

 ·         U.S. 40 (East Washington Street), between Post Road and Memorial Park Cemetery, will be restricted to one lane in each direction with a two-way center turn lane.
Date: Wednesday, April 16 – November 2008
Time: Continuous

 ·       Keystone Avenue/Rural Street, where it passes under I-70, will encounter lane restrictions for sandblasting and painting of bridge beams overhead as part of Super 70.
Date: Monday, April 21 – May 2008
Time: Continuous

·        
S.R. 9, north of the I-74 Bridge near Shelbyville, will encounter lane restrictions for intersection improvements and installation of new signals.
Date: Monday, April 14 – May 2008
Time: Daylight hours
 

·        S.R. 9 (State Street), between U.S. 40 (Main Street) and I-70 in Greenfield, will encounter nighttime lane closures for pavement patching and resurfacing.
Date: Tuesday, April 1 – May 2008
Time: 7 p.m. – 6 a.m. each work night

 ACCELERATE 465 RESTRICTIONS 

·         I-465 northbound, between the Crawfordsville Road and 56th Street exits on the Westside, will encounter traffic shifts and narrow lanes with temporary concrete barriers along the outside shoulder for Accelerate 465 interstate widening.
Date: Wednesday, September 12, 2007 – Fall 2008
Time: Continuous

 ·         West 38th Street, in both directions near the I-465 interchange, will be shifted onto one side of the road with narrow lanes and closures of adjacent turn or ramp lanes. Either direction of West 38th Street is not allowed to turn left at nearby intersections with High School Road or Shore Drive through August.
Date: Wednesday, July 25, 2007 – Fall 2008
Time: Continuous

 ·         West 34th Street will be closed to replace the bridge over I-465. A posted detour follows High School Road, West 38th Street and Eagle Creek Parkway.
Date: Monday, January 21 – July 2008
Time: Continuous

 PENDLETON PIKE RESTRICTIONS

 ·         Pendleton Pike (U.S. 36/S.R. 67), from I-465 to just east of Post Road, will be restricted to two narrow lanes in each direction with no dedicated turn lanes while crews widen the road and install new water and sewer lines.
Date: Tuesday, November 27, 2007 – Fall 2009
Time: Continuous

 ·         Sellers Street, north of Pendleton Pike, will be closed for road reconstruction. A posted detour follows Hull Street and Allen Street.
Date: Wednesday, April 9 – June 2008
Time: Continuous

 PREVIOUSLY REPORTED RESTRICTIONS

 ·         Allisonville Road northbound, at the bridge over I-465, will have the right lane closed awaiting a contract to repair a damaged steel bridge beam.
Date: Thursday, March 6 – June 2008
Time: Continuous

 ·         Market Street and Fletcher Street southbound ramp system, where it runs parallel to I-65/I-70, will be restricted to one lane as part of an Indianapolis DPW project to reconfigure interstate access in the area.  Click here for more Project Open Market information.
Date: Monday, March 10 – May 2008
Time: Continuous

 ·         Raceway Road, at the north end of the intersection with U.S. 136 (Crawfordsville Road), will be closed to reconstruct the intersection with added turn lanes.
Date: Monday, March 17 – June 2008
Time: Continuous

 ·         S.R. 37 at 131st Street may have utility crews working within state right of way to move lines that conflict with an upcoming road project.
Date: Monday, April 7 – May 2008
Time: Daylight hours

 ·         I-65 southbound, between Whiteland and Edinburgh, will have one lane closed at night for pavement resurfacing.
Date: Sunday, April 6 – June 2008
Time: 6 p.m. – 6 a.m. each work night

 ·         S.R. 67, between the Hendricks/Marion County line and I-465, will have one lane closed for up to a mile in each direction for intersection improvement work. Date: Monday, March 31 – November 2008
Time: Continuous  

 ·         I-70, I-465, Airport Expressway and Ameriplex/Ronald Reagan Parkway, near Indianapolis International Airport, will encounter shoulder closures for installation of new sign posts and foundations.
Date: Monday, March 17 – November 2008
Time: Daylight hours

 ·         I-74 and U.S. 136, between S.R. 267 and Raceway Road near Brownsburg, may encounter traffic shifts and narrow lanes for construction of a new I-74 interchange at Ronald Reagan Parkway.
Date: April 2007 – June 2008
Time: Continuous

 ·         S.R. 144, between Bargersville and Franklin, will encounter daytime lane closures controlled by flaggers for pavement resurfacing.
Date: Monday, April 14 – May 2008
Time: Daylight hours

 ·         S.R. 267 (Green Street), for a half mile north of I-74, will be restricted to narrow lanes for a road widening project.
Date: Monday, February 4, 2008 – June 2009
Time: Continuous

Oliver Avenue Bridge-Lane Closure
Due to a recent failure on the Oliver Avenue bridge, DPW Operations has closed the eastbound curb lane. This bridge is located on Oliver Avenue, near where Oliver, McCarty Street and Kentucky Avenue come together on the near southwest side. A portion of the spandrel wall (the side wall of an earth filled concrete arch structure)on the southeast end of this bridge has fallen off. The failure appears to be due to water infiltration. The closure will be "semi-permanent" as it will take some time to design and bid a repair and to secure the funds for the work. Between 100-150 feet of the eastbound curb lane will be closed. Since this is a four lane bridge, there is still one unobstructed eastbound lane open.

                                   MARKET STREET RAMP PROJECT
                                          (Lane  Restrictions and Closures)

Due to the relocation of communication lines for Project Open Market, the east (right) northbound lane of College Ave., and the two outside westbound lanes of Washington Street will be closed starting May 12, 2008 at 9:00 a.m. These lanes will remain closed 24 hours a day through May 17, 2008.

111 North Pine Street
ROW08-01939
TOTAL ROAD CLOSURE of Pine Street between Ohio and Market Street - Total Replacement and drainage INDOT Project. DETOUR Arsenal Avenue North to Michigan Street, West to East Street, South to Market Street.(Market Street has two-way traffic, back to College Ave)


506 East Market Street
ROW08-01358
There will be 1 traffic lane restricted from March 3, 2008 through May 31, 2008 for gas line installation.

700 East Washington Street
ROW08-01361
There will be 2 traffic lanes restricted from March 6, 2008 through May 31, 2008 for installation of gas lines.

730 East Washington Street
ROW08-02896
There will be 3 traffic lane restrictions from May 12 through May 23, 2008 to relocate closing the 2 North lanes of Washington and East curb lane of College at the beginning then just the North curb lane and sidewalk of Washington to finish. INDOT Project #IR29152.

775 East Washington Street
ROW08-01362
There will be 2 traffic lanes restricted from March 6, 2008 through May 31, 2008 for installation of gas lines.

 

                       CENTER TOWNSHIP - TOTAL CLOSURE(S)


Dorman Street over Pogues Run will be closed to all vehicle traffic permanently. (DPW Project # CH-25-002).  The vehicular bridge will be removed and replaces with a pedestrian bridge. Closure will occur on or after Monday January 28, 2008, (weather dependent) and will remain closed. The expected opening date for the pedestrian bridge is approximately mid to late May 2008. Street being closed: Dorman Street to Pogues Run, between Michigan Street and North Street.
DETOUR: None posted, not a thoroughfare, local neighborhood street road closure signs have been posted on site since January 14, 2008.


222 North East Street
ROW08-00446
TOTAL ROAD CLOSURE of Miami Street for Building work from January 24, 2008 through November 1, 2008. DETOUR to New York Street.

2250 North Rural Street
ROW08-02870/ROW08-02873/ROW08-02874
SOUTH BOUND CLOSURE Weekend ONLY from May 9 through May 12, 2008 for bridge cleaning and painting. INDOT R-2844B DETOUR: South bound 30th E to Emerson S to 21st W to Mass SW to Rural.
NORTH BOUND CLOSURE Weekend ONLY from May 16 through May 19, 2008 for bridge cleaning and painting. INDOT R-2844B DETOUR: North bound Mass. NE to 21st E to Emerson N to 30th W to Keystone.
NIGHT CLOSURE of Rural interchange 5/12 7 pm through 5/16 5 am and 5/19 7 pm through 5/22 5 am only. INDOT R-28444

10 West Market Street
ROW08-02100
ONE DAY TOTAL ROAD CLOSURES of Illinois between Washington St & Ohio; closure of  Market St between Capitol Ave & the circle; closure of Wabash St between Illinois and Meridian St; closure of Pierson St between Market St and Ohio Street for Helicopter lift to place HVAC units on building. 


                       CENTER TOWNSHIP - TRAFFIC LANE(S) RESTRICTION

 
460 West 16th Street
ROW08-01510
There will be 1 traffic lane restricted from March 10, 2008 through October 1, 2008 for New Pedestrian Enhancement (DPW Project ST-24-010).

471 West 16th Place
ROW08-01511
There will be 2 traffic lane restrictions from March 10, 2008 through October 1, 2008 for New Pedestrian Enhancement (DPW Project ST-24-010)

245 West 38th Street
ROW08-01246
There will be 1 traffic lane restricted from February 26, 2008 through May 31, 2008 for service repair.

109 North Belmont Avenue
ROW08-03000
There will be 1 traffic lane restricted from May 12 through June 30, 2008 for service leak repair.

447 North Bosart Avenue
ROW08-02466
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service renewal.

4522 Brookville Road
ROW08-02415
There will be 1 traffic lane restricted from April 17 through June 30, 2008 for service renewals.

1 North Capitol Avenue***
ROW08-03041
There will be 1 traffic lane restricted from May 19, 2008 through July 18, 2008 for traffic lane use to park dumpster in alley for construction of debris.

100 South Capitol Avenue
ROW08-02850(ROW08-02998)
There will be 1 traffic lane restricted from May 6 through May 20, 2008 for service abandonment./There will be 2 traffic lanes restricted from May 12 through August 1, 2008 for Convention Center demo.

3433 Central Avenue
ROW08-02851
There will be 1 traffic lane restricted from May 6 through July 31, 2008 for service abandonment.

3556 North College Avenue
ROW08-02839
There will be 2 traffic lanes restricted from July 31 through September 1, 2008 for manhole repair.

50 South College Avenue
ROW08-02531
There will be 2 traffic lanes restricted from April 23 through June 30, 2008 for main repair.

100 South College Avenue
ROW08-02530
There will be 1 traffic lane restricted from April 23 through June 30, 2008 for main repair.

547 Dorman Street
ROW08-00256
There will be 2 traffic lanes restricted from January 21, 2008 through June 1, 2008.

222 North East Street
ROW08-02306
There will be 1 traffic lane restricted from April 15 through May 23, 2008 to tie sewer into combo sewer.

601 North East Street
ROW08-02738
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for installation of gas lines.

1271 South East Street
ROW08-02970
There will be 1 traffic lane restricted from May 9 through July 31, 2008 for service renewal.

4517 English Avenue
ROW08-02467
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service renewal.

845 North Illinois Street
ROW08-01877
There will be 2 traffic lane restricted from March 9 through June 30, 2008 for expansion of chilled water plant.

1450 North Illinois Street
ROW08-02167
There will be 4 traffic lanes restricted from April 9 through July 9, 2008 to open cut trench across 14th Street on Illinois.

425 South Keystone Avenue
ROW08-00922
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

333 Massachusetts Avenue
200N/201E (ROW07-02980)
ROW07-08931,ROW07-08932,ROW07-08934,
There will be 1 traffic lane and 2 curb lanes for construction of new condominiums from   July 20th,   2007   through January 16th, 2009.

700 Massachusetts Avenue
ROW08-02735
There will be 1 traffic lane restricted from May 1 through July 31, 2008 to install gas lines.

825 Massachusetts Avenue
ROW08-02132(ROW08-02736)
There will be 1 traffic lane restricted from April 4 through May 30, 2008 for main leak repair.(There will be 1 traffic lane restricted from May 1 through July 31, 2008 for installation of gas lines.)

897 Massachusetts Avenue
ROW08-002737
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for installation of gas lines.

719 East McCarty Street***
ROW08-03058
There will be 1 traffic lane restricted from May 15, through June 6, 2008 to repair structure.

240 North Meridian Street Update Extended
0/1N (ROW07-03486)( ROW08-00415)
There will be 1 traffic lane restricted on New York Street(between Pierson Street Alley and Meridian Street) from May 31, 2007 through March 3, 2008. Amended to include use of a 2nd traffic lane from 11/13/2007 to 08/29/2008 from 9 a.m. to 3:30 p.m. only. To install sheet piles and remove transformers in sidewalk. 

2402 North Meridian Street
ROW08-02639
There will be 1 traffic lane restricted from May 7 through June 1, 2008 for storm sewer work.

222 East Michigan Street
ROW08-02392
There will be 1 traffic lane restricted from April 18 through May 18, 2008 for steam main repair.

4811 East Michigan Street
ROW08-02472
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service renewals.

5029 East Michigan Street
ROW08-02471
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service renewals.

502 South Missouri Street
ROW08-02442(ROW08-02641)
There will be 2 traffic lanes restricted from April 21 through May 23, 2008 for placement of conduit across Missouri Street for Fiber Optic cable ring for Luca Oil Stadium.

506 East Morris Street
ROW08-02967
There will be 1 traffic lane restricted from May 9 through July 31, 2008 for service renewal.

602 East Morris Street
ROW08-02968
There will be 1 traffic lane restricted from May 9 through July 31, 2008 for service renewal.

910 East Morris Street
ROW08-02969
There will be 1 traffic lane restricted from May 9 through July 31, 2008 for service renewal.

959 East Morris Street
ROW08-02461
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service repair.

525 East New York Street
ROW08-02640
There will be 1 traffic lane restricted from April 28 through May 31, 2008 for excavation and placing conduit in a north/south alley from 515 E. New York Street South to Miami Street. This will require the closure of the far south curb lane of New York.

3 East North Street
ROW08-02727
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for installation of gas lines.

330 West North Street***
ROW08-03081
There will be 2 traffic lanes restricted from May 15 through July 31, 2008 for excavating.

614 East Ohio Street
ROW08-01502
There will be 1 traffic lane restricted from March 6, 2008 through May 31, 2008 for service abandonment.

1516 East Ohio Street
ROW08-02438
There will be 1 traffic lane restricted from April 18 through June 30, 2008 for main replacement.

1602 East Ohio Street
ROW08-02437
There will be 1 traffic lane restricted from April 18 through June 30, 2008 for main replacement.

333 North Pennsylvania Street
ROW08-02809
There will be 1 traffic lane restricted from May 12 through May 18, 2008 for removal of loose stones on building.

952 North Pennsylvania Street
ROW08-02390
There will be 2 traffic lanes restricted from April 18 through May 18, 2008 for main repair in alley.

2203 North Pennsylvania Street
ROW08-00918
There will be 1 traffic lane restricted from February 11 through June 30, 2008 for main repair, intersection of E 22nd Street & Pennsylvania Street.

927 South Pennsylvania Street
ROW08-02856
There will be 1 traffic lane restricted from May 6 through May 20, 2008 for service repair.

545 North Senate Avenue
ROW08-02668
There will be 1 traffic lane restricted from April 28 through May 31, 2008 to fix water valve leak in sidewalk.

50 Shelby Street
ROW08-01353
There will be 1 traffic lane restricted from March 3, 2008 through May 31, 2008 for installation of gas lines. 

1002 North Sherman Drive
ROW08-01026
There will be 1 traffic lane restricted from February 15, 2008 through May 30, 2008 for installation of gas lines.

1206 North Sherman Drive
ROW08-01027
There will be 1 traffic lane restricted from February 15, 2008 through May 30, 2008 for installation of gas lines.

1313 North Sherman Drive
ROW08-01028
There will be 1 traffic lane restricted from February 15, 2008 through May 30, 2008 for installation of gas lines.

1605 North Sherman Drive
ROW08-01535
There will be 1 traffic lane restricted from March 7, 2008 through June 30, 2008 gas main repair.

1001 Southeastern Avenue
ROW08-01354(ROW08-01781)
There will be 1 traffic lane restricted from March 3, 2008 through May 31, 2008 for installation of gas lines. (There will be 2 traffic lanes restricted from March 20, 2008 through April 30, 2008).

1101 Southeastern Avenue
ROW08-00940
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1214 Southeastern Avenue
ROW08-00939
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1315 Southeastern Avenue
ROW08-00938
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1400 Southeastern Avenue
ROW08-00937
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1501 Southeastern Avenue
ROW08-00936
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1611 Southeastern Avenue
ROW08-00934
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

1702 Southeastern Avenue
ROW08-00933
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

2300 Southeastern Avenue
ROW08-00923
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 for installation of gas lines.

122 North State Avenue
ROW08-02436
There will be 1 traffic lane restricted from April 18 through June 30, 2008 for main replacement.

120 East Vermont Street
ROW08-02882
There will be 1 traffic lane restricted from June 1 through June 15, 2008 for remodeling of building.

702 Virginia Avenue***
ROW08-03059
There will be 1 traffic lane restricted from May 15 through June 6, 2009 to repair slpper joint.


425 East Walnut Street
ROW08-02729
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for gas line installation.

450 East Walnut Street
ROW08-02728
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for gas line installation.

509 East Walnut Street
ROW08-02730
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for gas line installation.

528 East Walnut Street
ROW08-02904
There will be 1 traffic lane restricted from May 27 through August 27, 2008 for renovation and residential roofing.

619 East Walnut Street
ROW08-02733
There will be 1 traffic lane restricted from May 1 through July 31, 2008 for gas line installation.

130 East Washington Street
ROW08-01111
There will be 1 traffic lane restricted from February 21, 2008 through July 9, 2008.

1315 East Washington Street
ROW08-01623
There will be 1 traffic lane restricted from March 11, 2008 through May 31, 2008 for installation of gas lines.

501 West Washington Street***
ROW08-03106
There will be 1 traffic lane restricted from May 15 through June 15, 2008 for manhole work for new telephone cable installation.


Traffic /Downtown Indianapolis 

The Indianapolis Artsgarden features free performances all season.  Visit www.DiscoverWholesaleDistrict.com for more information. 

Log on to www.indydt.com/parkingdatabase.html  before you come Downtown and find specific parking facility information, including photographs that will help you know what to look for. 

Parking meters may also be available near your destination. They are FREE after 6 p.m. on weekdays and all day Saturday, Sunday and holidays.  

DECATUR TOWNSHIP - TOTAL CLOSURE(S)

Bridgeport Road Bridge Over I-70 from Stafford Road to Stanley Road
8800W/5500S
Bridgeport Road Bridge over I-70 from Stafford Road to Stanley Road is closed indefinitely due to the I-70 reconstruction project.

Epler Road from Raceway Road to Bridgeport Road
5500S/9300W
Epler Road from Raceway Road to Bridgeport Road is closed indefinitely due to the I-70 reconstruction project.

Hanna Avenue Bridge Over I-70 from Kollman Road to South Perimeter Road
4000S/6700W
Hanna Avenue Bridge over I-70 from Kollman Road to South Perimeter Road is closed indefinitely due to the I-70 reconstruction project.

Kollman Road (small area just south of I-70)
6700W/3640S
Kollman Road (small area just south of I-70) is closed indefinitely due to the I-70 reconstruction project.

Raceway Road from 1075 East to Epler Road
9300W/5500S
Raceway Road from 1075 East to Epler Road is closed indefinitely due to the I-70 reconstruction project.

Scott Road from South of I-70 to Hanna Avenue
7000W/4000S
Scott Road from South of I-70 to Hanna Avenue is closed indefinitely due to the I-70 reconstruction project.

Stanley Road from Bridgeport Road to Brushwood Road
8800W/6500S
Stanley Road from Bridgeport Road to Brushwood Road is closed indefinitely due to the I-70 reconstruction project.

Thompson Road from Stanley Road to Brushwood Road
5000S/8800W
Thompson Road from Stanley Road to Brushwood Road is closed indefinitely due to the I-70 reconstruction project.

2500 South High School Road
ROW08-00461
TOTAL ROAD CLOSURE on Hoffman Road from February 1, 2008 through July 20, 2008.

DECATUR TOWNSHIP-TRAFFIC LANE RESTRICTIONS(S)



4902 South High School Road
ROW08-02111
There will be 1 traffic lane restricted from April 4 through June 30, 2008 for main repair at intersection of W. Mooresville Rd & S. High School Road.

3835 Kentucky Avenue
ROW08-02980
There will be 1 traffic lane restricted from May 14, 2008 through August 14, 2008 for ditching on south side of Kentucky Avenue.

7118 Milhouse Road
ROW08-02985
There will be 1 traffic lane restricted from May 14 through August 14, 2008 for ditching.

7442 South Mooresville Road
ROW08-03009
There will be 1 traffic lane restricted from May 13 through July 31, 2008 for service abandonment.

                                    FRANLKIN TOWNSHIP-TOTAL CLOSURE(S)

6620 Shelbyville Road
ROW08-01427
TOTAL ROAD CLOSURE for row excavation for DPW Project #B-27199-A for Bridge Replacement from March 17, 2008 through June 14, 2008.
Northwestern Bound Traffic Detour Route:  The detour begins by making a left turn at the intersection of Shelbyville Road and Southport Road. Then at the intersection of Southport Road and Arlington Avenue, make a right turn and continue north to re-intersect Shelbyville Road at end of detour.
Southeastern Bound Traffic Detour Route: The detour begins by making a right turn at the intersection of Shelbyville Road and Arlington Avenue, proceed south on Arlington Avenue until making a left turn at the intersection of Southport Road, continue east on Southport Road to re-intersect with Shelbyville Road at end of detour.


                       FRANKLIN TOWNSHIP -TRAFFIC LANE(S)RESTRICTION

4010 South Carroll Road
ROW08-02454
There will be 1 traffic lane restricted from April 23 through May 23, 2008 for cross pipe replacement closing one lane at a time.

7501 South Franklin Road
ROW08-02453
There will be 1 traffic lane restricted from April 23 through May 23, 2008 for cross pipe replacement, closing one lane at a time.

5949 East Southport Road
ROW08-02412
There will be 1 traffic lane restricted from April 17 through June 30, 2008 for main repair.


                                LAWRENCE TOWNSHIP TOTAL CLOSURE(S)   


 

                        LAWRENCE TOWNSHIP- TRAFFIC LANE RESTRICTION(S)

7490 East 38th Street
ROW08-02855
There will be 2 traffic lanes restricted from May 7 through July 30, 2008 for boring.

12442 East 62nd Street
ROW08-02978
There will be 1 traffic lane restricted from May 14 through August 14, 2008 for ditching.

8074 Hague Road
ROW08-02599
There will be 1 traffic lane restricted from April 24 through May 31, 2008 for water main repair.

8197 Sargent Road
ROW08-01681
There will be 1 traffic lane restricted from March 18, 2008 through May 31, 2008 for new service with main extension.


                                PERRY TOWNSHIP - TOTAL CLOSURE(S)





                          PERRY TOWNSHIP - TRAFFIC LANE(S) RESTRICTION

7990 Bluff Road
ROW08-02648
There will be 1 traffic lane restricted April 28 through June 30, 2008 for gas main work.

Emerson Avenue  (Project #ST-40-011) Churchman Avenue to Raymond Street

Emerson Avenue from Churchman Avenue to Raymond Street will be restricted to traffic through December 1, 2006. After December 1, 2006 temporary daytime lane closures for maintenance of traffic control will be used at various locations. The project includes: pavement reconstruction, storm sewer repairs, replacement of curbs and sidewalks, as well as traffic signal items. The City of Beech Grove has a separate project that is to be constructed concurrently within the same project limits. This project includes: new landscaping, decorative tower gateway features, concrete retaining walls and related items of work.

1400 East Hanna Avenue
ROW08-00816
There will be 1 traffic lane restricted from February 11, 2008 through May 30, 2008 to re-route main for building extension.

5247 South Keystone Avenue
ROW08-02903
There will be 1 traffic lane restricted from May 12 through June 12, 2008 to install new water service.

5935 McFarland Road
ROW08-01593
There will be 1 traffic lane restricted from March 10, 2008 through May 31, 2008 for new service bores.

4202 Madison Avenue
ROW08-02435
There will be 1 traffic lane restricted from April 18 through May 30, 2008.

7130 Shelby Street
ROW08-01903
There will be 1 traffic lane restricted from March 27, 2008 through June 30, 2008 for new gas service.

1403 East Stop 11 Road
ROW08-02247
There will be 2 traffic lanes restricted from April 14 through June 30, 2008 to replace water valve.

1335 West Stop 11 Road
ROW08-02246
There will be 2 traffic lanes restricted from April 14 through June 30, 2008 to replace water valve.

2203 East Troy Avenue
ROW08-02462
There will be 1 traffic lane restricted from April 21 through June 30, 2008 for service repair.


8055 US 31
ROW08-02248
There will be 2 traffic lanes restricted from April 14 through June 30, 2008 to replace water valve.

                                           PIKE TOWNSHIP-TOTAL CLOSURE(S)



                                   
PIKE TOWNSHIP- TRAFFIC LANE RESTRICTION(S)


3609 West 62nd Street
ROW08-01927
There will be 1 traffic lane restricted from March 28, 2008 through June 30, 2008 for installation of gas lines.

5902 Guion Road
ROW08-02714
There will be 1 traffic lane restricted from May 1 through June 1, 2008 for work done to repair manhole.

4351 Lafayette Road
ROW08-02805
There will be 1 traffic lane restricted from May 2 through July 31, 2008 for main repair.

4525 Lafayette Road
ROW08-01538
There will be 1 traffic lane restricted from March 7, 2008 through June 30, 2008 to install gas service.

4351 Lafayette Road
ROW08-02410
There will be 1 traffic lane restricted from April 17 through June 30, 2008 for main repair.

6025 Lafayette Road
ROW08-02627
There will be 1 traffic lane restricted from April 25 through June 30, 2008 for main repair.



WARREN TOWNSHIP-TOTAL CLOSURE(S) 



9502 East Washington Street
ROW07-08989
TOTAL ROAD CLOSURE
There will be rolling road blocks on (Westbound) East Washington Street at Delbrick Lane and Delbrick Lane will be closed from December 13, 2007 through June 14, 2008.
DETOUR: US 40/Washington Street East to Mitthoeffer Street, North to 10th Street, West to Delbrick Lane.

Recent weather has delayed the Rawles Avenue closure and detour. Rawles Avenue, between Franklin Road and Post Road, will now be closed May 19, 2008, until approximately June 16, 2008, for the installation of a new sanitary sewer. Please see attached for a detour map. East bound traffic will detour north on Franklin to Washington then east to Post and south to Rawles.  West bound traffic will detour north on Post to Washington, west to Franklin and then south to Rawles.

WARREN TOWNSHIP-TRAFFIC LANE(S) RESTRICTION


9820 East 12th Street
ROW08-00797
There will be 2 traffic lanes restricted from March 15, 2008 thru May 15, 2008 for sewer main installation for 10th street & Mitthoeffer Rd. area of "STEP" Project. (12th street from Mitthoeffer Rd to Malvina Ave)(DPW PROJECT #BL-28-27A).

421 North Emerson Avenue
ROW08-01668
There will be 1 traffic lane restricted from March 18, 2008 through May 18, 2008 to install new inlet.

7506 East Raymond Street
ROW08-02452
There will be 1 traffic lane restricted from April 23 through May 23, 2008 for cross pipe replacement, closing one lane at a time.


                            WASHINGTON TOWNSHIP - TOTAL CLOSURE(S)


6400 Westfield Boulevard
(ROW07-08905)
TOTAL ROAD CLOSURE from December 17th, 2007 through May 30, 2008 for Installation of Indy Flood Wall Project.
Detour: NE bound go north on College to 65th Street, east to Westfield. Southbound traffic go west on 65th St to College, south to Westfield. northbound on Winthrop west to College Avenue

WASHINGTON TOWNSHIP - TRAFFIC LANE(S) RESTRICTION


919 East 46th Street***
ROW08-03073
There will be 1 traffic lane restricted from July 31 through September 1, 2008 for utility work.

2440 East 56th Street
ROW08-01709
There will be 1 traffic lane restricted from March 19, 2008 through May 31, 2008 for main repair.

2702 East 56th Street
ROW08-01664(ROW08-01874)
There will be 1 traffic lane restricted from March 14, 2008 through May 31, 2008 for main repair.(There will be 1 traffic lane restricted from March 26 through June 30, 2008 for gas main repair.

440 East 57th Street
ROW07-05498
There will be 2 traffic lanes restricted for the adding on of IPS #84 from August 21, 2007 through June 1, 2009.

4560 East 62nd Street
ROW08-01707
There will be 1 traffic lane restricted from March 19, 2008 through May 31, 2008 for service repair.

2343 West 62nd Street
ROW08-01005
There will be 1 traffic lane restricted from February 14, 2008 through May 30, 2008 for main repair.

3200 East 86th Street
ROW08-02568
There will be 1 traffic lane restricted from May 24 through July 24, 2008 for 200 foot ditching on the South West Corner of 86th street and Keystone Crossing.

5110 Kessler Blvd NDR***
ROW08-03031
There will be 1 traffic lane restricted from May 13 through May 27, 2008 for main repair.

806 Broad Ripple Avenue
ROW08-02987
There will be 1 traffic lane restricted from May 12 through July 31, 2008 for main repair.

4053 North Capitol Avenue
ROW08-01875
There will be 1 traffic lane restricted from March 26 through June 30, 2008 for service repair.

5610 Central Avenue
ROW08-02101
There will be 1 traffic lane restricted from April 3 through June 30, 2008 for new service.

6372 Guilford Avenue
ROW08-02397
There will be 2 traffic lanes restricted from July 28 through September 5, 2008 for easement work.

4206 Kessler Blvd NDR
ROW08-02674
There will be 1 traffic lane restricted from April 29 through July 31, 2008 for main repair.

4377 Kessler Blvd NDR
ROW08-02264
There will be 1 traffic lane restricted from April 11 through June 30, 2008 for main repair.

4390 Kessler Blvd NDR
ROW08-0265
There will be 1 traffic lane restricted from April 14 through June 30, 2008 for main repair.

5218 Kessler Blvd NDR
ROW08-02266
There will be 1 traffic lane restricted from April 11 through June 30, 2008 for main repair.

6401 North Meridian Street
ROW08-02616
There will be 1 traffic lane restricted from April 28 through July 31, 2008 for installation of gas lines for the whole 6400 block N Meridian Street.


7105 North Meridian Street
ROW08-02617
There will be 1 traffic lane restricted from April 28 through July 31, 2008 for installation of gas lines for the 7100 block N. Meridian Street.

7202 North Meridian Street
ROW08-02618
There will be 1 traffic lane restricted from April 28 through July 31, 2008 for installation of gas lines of 7200 block of North Meridian Street.

 

Update 38-(Phase II)

38th Street from Salem Street to Fall Creek Parkway will be restricted to traffic through fall of 2007.  Various lane closures for traffic control will be maintained throughout the project construction limits.  The project includes: pavement reconstruction, storm sewer repairs, replacement of curbs, sidewalks, new landscaping, decorative pre-cast median walls, gateway feature, decorative crosswalks, replacement of traffic signal items with visual and audible pedestrian indication and related items of work.

                                 WAYNE TOWNSHIP - TOTAL CLOSURES


 

WAYNE TOWNSHIP-TRAFFIC LANE(S) RESTRICTIONS

3329 West 10th Street
ROW08-02687
There will be 1 traffic lane restricted from May 5 through May 30, 2008 for basin replacement.

2863 West 30th Street***
ROW08-03089
There will be 1 traffic lane restricted from May 27 through July 31, 2008 for main repair.

2916 West 30th Street***
ROW08-03034
There will be 1 traffic lane restricted from May 13 through May 27, 2008 for main repair.

1321 North Girls School Road
ROW08-01597
There will be 1 traffic lane restricted from March 10, 2008 through May 31, 2008 for service repair.

2301 North Girls School Road
ROW08-02919
There will be 1 traffic lane restricted from May 8 through May 31, 2008 to repair water main in asphalt.

2101 West Morris Street
ROW08-01676
There will be 1 traffic lane restricted from March 18, 2008 through May 31, 2008 for service repair.

7901 West Morris Street***
ROW08-03110
There will be 1 traffic lane restricted from May 16 through May 23, 2008 to clean sewer.

4936 Rockville Road
ROW08-02540
There will be 1 traffic lane restricted from April 23 through June 30, 2008 for service repair.

1401 North Tibbs Avenue
ROW08-02716
There will be 1 traffic lane restricted from May 1 through June 5, 2008 for manhole repair, work being done at 1400 North Tibbs.

2215 West Washington Street
ROW08-01988
There will be 1 traffic lane restricted from April 1, 2008 through May 30, 2008.

If you would like to receive weekly traffic e-mail updates, visit www.indygov.org and register for our Street Closing and Traffic Restrictions e-newsletter.  For information about other Indianapolis Department of Public Works services, please visit the DPW Web site at www.indygov.org/dpw.

For information on Indiana Department of Transportation projects, state roads and highway information, please contact INDOT at 232-5533

 

 
 

Last Updated: 5/16/2008 |  Print This Page | Email to Friend

 