Project Open Market: Construction Costs and Timeline
The project is expected to cost at least $20 million. The first $10 million is provided by the federal government. The remaining is split at an 80/20 ratio – with 8 out of 10 dollars coming from the federal government and the city of Indianapolis providing the remaining 2.
Current Construction Schedule
Phase I - Spring/Summer 2008 Ohio Street ramp closed (February 2008) Construct new southbound I-65/I-70 entrance ramp (Summer 2008) Fletcher Avenue southbound exit ramp widening (Spring/Summer 2008)
Phase II - Fall 2008 Widen Washington Street and relocate Southeastern Avenue intersection (Fall 2008)
Phase III – Fall 2008 Temporarily close existing northbound exit ramp from I-65/I-70 (Fall 2008) Construct new northbound exit ramp from I-65/I-70 (Fall 2008)
Phase IV – Winter 2008 to Spring/Summer 2009 Close and remove Market Street exit ramp (Winter 2008-2009) Close and remove Market Street entrance ramp (Winter 2008-2009) Construct infrastructure along Market Street, Davidson Street and Pine Street (Spring/Summer 2009)
Project completion - Fall 2009
|