IndyGov
Department of Public Works, City of Indianapolis
Clean Stream Team

 Current and Upcoming Projects
 Completed Projects
 Belmont-Southport Interplant Connect
 Fall Creek White River Tunnel
 Information for Consultants
 Project Fact Sheets

Council District 19 Projects

Council District 19

Project:  Pogue's Run Tunnel Conversion-Construction

Project #:  CS-31-072C

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2010

Township:  Center

Council District:  19

Status:  Planning

Description:  Installation of inflatable dams and appertenances

 

Project:  Belmont/Southport Interplant Connect  Phase I- Construction (PER 5C)

Project #:  CS-38-002C

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2010

Township:  Center/Perry

Council District: 19, 22

Status:  Design

Description:  First phase of construction of the interplant connect of Belmont and Southport AWT facilities, includes construction of the pipeline via tunneling method

 

Project:  Belmont/Southport AWT Oxygen Separation Site Work

Project #:  BE-51-002F

Type: Sanitary

Secondary Type:  AWT-Capital

Bid/Study Date:  2009

Township:  Perry

Council District:  19

Status:  Design

Description:  Site work at the Southport Advanced Wastewater Treatment Facility to support the installation of an air separation facility to be constructed on that site

 

Project:  Merrill Street Combined Sewer Rehabilitation (PER 5B)

Project #:  CS-32-005

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2009

Township:  Center

Council District:  19

Status:  Design

Description:  CSO Rehab identified in the Greeley & Hansen Combined Sewer Infrastructure Assessment (July 1996).

 

Project:  Brill/Troy Septic Tank Elimination Program (PER 5B)

Project #:  BL-32-001

Type: Sanitary

Secondary Type:  STEP

Bid/Study Date:  2009

Township:  Perry

Council District:  19, 23

Status:  Design

Description:  Installation of sanitary sewer to solve septic system problems and improve water qualities in areas near Brill Rd. and Troy Ave.

 

Project:  Highland Creek and White River Stormwater Improvements

Project #:  SD-32-009

Type:  Storm

Secondary Type:  Water Quality

Bid/Study Date:  2009

Township:  Center/Perry

Council District:  19, 23

Status:  Planning

Description:  Stormwater relief project that will impact Frog Hollow and adjacent neighborhoods

 

Project:  CSO 217/218 Elimination

Project #:  CS-30-001

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2008

Township:  Decatur

Council District:  19

Status:  Design

Description:  Sewer separation and rehabilitation to eliminate CSO 217/218;   segment of project combined with Mars Hill Drainage, SD-30-064

 

Project:  White River Comb. Sewer Interceptor Rehabilitation (PER 5B)

Project #:  CS-24-103

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2008

Township:  Center

Council District:  15, 19

Status:  Construction

Description:  Rehab of interceptor pipeline due to defects found during cleaning in 2003

 

Project:  Mars Hill - Phase II

Project #:  SD-30-064B

Type:  Storm

Secondary Type:  Roadside/Area Drainage

Bid/Study Date:  2008

Township:  Wayne

Council District:  19

Status:  Design

Description:  Drainage improvements, storm sewer installation - Phase II

 

Project:  Belmont Liquid Oxygen (LOX) Storage and Vaporization System

Project #:  BE-51-002E

Type:  Sanitary

Secondary Type:  AWT-Capital

Bid/Study Date:  2007

Township:  Center

Council District:  19

Status:  Construction

Description:  Construction of 30 TPD LOX Storage tanks and vaporizers to supplement the existing 120 TPD VSA oxygen plant and LOX storage tanks

 

Project:  Eagle Creek Interceptor-Facility Planning (PER 04B)

Project #:  CS-31-007A

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2007

Township:  Center/Wayne

Council District:  14, 19

Status:  Planning

Description:  Project allocates funds toward the facility planning for Eagle Creek Interceptor, will provide a collection interceptor that conveys CSO flows to the Belmont AWT facility

 

Project:  CSO Storage Tunnel- Phase 1B Geotechnical Investigation

Project #:  CS-18-072A

Type:  Sanitary

Secondary Type:  CSO

Bid/Study Date:  2007

Township:  Center

Council District:  9, 15, 19

Status:  Planning

Description:  Project will involve completion of preliminary geotechnical investigations for the Fall Creek/White River CSO Storage Tunnel

 

Project:  South Street Sewer Relocation

Project #:  CS-30-003

Type:  Sanitary

Secondary Type:  Sanitary Sewers

Bid/Study Date:  2007

Township:  Center

Council District:  19

Status:  Construction

Description:  Relocation of sewer for tunnel connection stadium to convention center

 

Project:  Bluff and West Street Drainage

Project #:  SD-31-005

Type:  Storm

Secondary Type:  Roadside/Area Drainage