Decatur Township

|
Project: CSO 217/218 Elimination |
Project #: CS-30-001 |
|
Type: Sanitary |
Secondary Type: CSO |
Bid/Study Date: 2008 |
|
Township: Decatur |
Council District: 19 |
Status: Design |
|
Description: Sewer separation and rehabilitation to eliminate CSO 217/218; segment of project combined with Mars Hill Drainage, SD-30-064 |
|
|
|
|
|
Project: Belmont Wet Weather Chlor. / Dechlorination Facilities – Design (PER-3C) |
Project #: BE-10-010A |
|
Type: Sanitary |
Secondary Type: CSO-AWT |
Bid/Study Date: 2007 |
|
Township: Decatur |
Council District: 27 |
Status: Design |
|
Description: Will construct a new chlorine contact tank at the Belmont AWT plant for disinfection of wet weather flows |
|
|
|
|
|
Project: LS 101 (Bridgeport) Upgrade - Design |
Project #: LS-36-003A |
|
Type: Sanitary |
Secondary Type: Lift Stations |
Bid/Study Date: 2007 |
|
Township: Decatur |
Council District: 22 |
Status: Planning |
|
Description: Upgrade of LS 101 |
|
|
|
|
|
Project: Mars Hill Drainage Improvements - Phase III |
Project #: SD-30-064C |
|
Type: Storm |
Secondary Type: Roadside/Area Drainage |
Bid/Study Date: 2007 |
|
Township: Decatur/Wayne |
Council District: 19 |
Status: Construction |
|
Description: Phase III Drainage Improvements in conjunction with resurfacing work |
|
|
|
|
|
Project: CSO 275 Elimination (PER 4B) |
Project #: CS-37-001 |
|
Type: Sanitary |
Secondary Type: CSO |
Bid/Study Date: 2006 |
|
Township: Decatur |
Council District: 23 |
Status: Close-out |
|
Description: Another early action project, the city will separate the combined sewer area tributary to Combined Sewer Outfall (CSO) #275, eliminating this remote CSO along White River near 4900 South Foltz Street |
|
|
|
|
|
Project: Mars Hill / Roena / Farnsworth /Collier / Berwyn /Foltz - Phase |
Project #: SD-30-064A |
|
Type: Storm |
Secondary Type: Roadside/Area Drainage |
Bid/Study Date: 2006 |
|
Township: Decatur/Wayne |
Council District: 19, 22 |
Status: Construction |
|
Description: State Ditch cleaning, drainage improvements, storm sewer installation - PHASE I |
|
|
|
|
|
|