General Conditions
ARTICLE 1 - ABBREVEATIONS AND DEFINITIONS
ARTICLE 2 - PRELIMINARY MATTERS
2.1 Delivery of Agreements G-12 2.2 Delivery of Insurance and Bonds G-12 2.3 Copies of Documents G-12 2.4 Commencement of Contract Timed: Notice to Proceed G-13 2.5 Starting the Project G-13 2.6 Before Starting Construction G-13 2.7 Initial Schedule and Submissions G-14 2.8 Preconstruction Conference G-14 2.9 Finalizing Schedules G-14
ARTICLE 3 - CONTRACT DOCUMENTS
3.1 Integration of Contract Documents G-15 3.2 Intent and Meaning G-15 3.3 Duty to Report Discrepancies G-16 3.4 Major Modifications G-16 3.5 Minor Deviations G-16 3.6. Reuse of Documents G-16
ARTICLE 4 - AVAILABILITY OF LANDS: PHYSICAL CONDITIONS
4.1 Availability of Lands G-16 4.2 Subsurface and Physical Conditions(Excluding Underground Facilities) G-17 4.3 Differing Subsurface or Physical Conditions G-17 4.4 Underground Facilities G-18 4.5 Reference Points and Layout G-19 4.6 Lines and Grades G-20 4.7 Hazardous Materials G-21 4.8 Rights in and Use of Materials found inthe Project Site G-22
ARTICLE 5 - BONDS AND INSURANCE
5.1 Performance and Payment Bonds G-23 5.2 Maintenance Bond G-23 5.3 Substitute Bonds G-23 5.4 Contractor's Liability Insurance G-24 5.5 Owner's Protective Insurance G-26 5.6 Property Insurance G-27 5.7 Waiver Subrogation G-27 5.8 Acceptance of Insurance G-28 5.9 Partial Utilization Property Insurance G-28 5.10 No Limit to Liability G-28
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
6.1 Supervision G-28 6.2 Resident Superintendent G-29 6.3 Personnel and Work Hours G-29 6.4 Full Responsibility G-29 6.5 General Standards of Quality G-29 6.6 Adjusting Progress Schedule G-29 6.7 Substitute or "Or Equal" Items G-30 6.8 Engagement of Subcontractors, Suppliers, and Others G-30 6.9 Responsibility For Others G-31 6.10 Allocation of Work G-31 6.11 Subcontractor Provisions G-31 6.12 Patent Fees and Royalties G-31 6.13 Permits G-32 6.14 Laws and Regulations G-32 6.15 Taxes G-32 6.16 Use of Premises G-32 6.17 Control of Waste G-33 6.18 Loads on Structures G-33 6.19 Record Documents and As-Built Drawings G-33 6.20 Safety and Protection G-34 6.21 Emergencies G-36 6.22 Shop Drawings and Working Drawings G-36 6.23 Continuing the Works G-39 6.24 Allocation of Risk and Indemnification G-39 6.25 Subcontractor and other Liens G-40 6.26 Installation of Utility Service G-40 6.27 Damage Survey and Correction G-40 6.28 Damage Notification G-40 6.29 Prevailing Wage Rates G-40 6.30 Conformance with Plans and Specifications G-41 6.31 Documentation G-42
ARTICLE 7 - WORK BY THIRD PARTIES
ARTICLE 8 - OWNER'S AND ENGINEER'S STATUS DURING CONSTRUCTION
8.1 Owner's Representative G-43 8.2 Visits to Site G-44 8.3 Project Representations G-44 8.4 Clarifications and Interpretations G-44 8.5 Authorized Variations in Work G-44 8.6 Rejecting Defective Work G-45 8.7 Engineer's Interpretation and Decisions G-45 8.8 Non-liability of Engineer G-45 8.9 Purposes of Engineer's Activities G-45 8.10 Construction Methods G-46 8.11 Acts of Omissions by Others G-46 8.12 Communications G-46 8.13 Replacement for Engineer G-46
ARTICLE 9 - CHANGES IN THE WORK
9.1 Owner's Right to Initiate Changes G-46 9.2 Inability to Agree on Price or TimeAdjustments G-47 9.3 Non-Required Work G-47 9.4 Change Order and Amendments G-47
ARTICLE 10 - CHANGE OF CONTRACT PRICE
10.1 Items Included in Contract Price G-47 10.2 Changes in Contract Price G-47 10.3 Value of Affected Work G-48 10.4 Cost of Work G-48 10.5 Excluded Costs G-51 10.6 Cash Allowances G-51
ARTICLE 11 - CHANGE OF CONTRACT TIME, LIQUIDATED DAMAGES; DELAYS AND HINDRANCES
11.1 Liquidated Damages - Assessment G-52 11.2 Liquidated Damages - Reasonable Amount G-52 11.3 Delay Following Termination G-53 11.4 Extension of Contract Time G-53 11.5 Notice of Delays or Hindrances G-54 11.7 Limitations on Time Extensions G-54
ARTICLE 12 - WARRANTIES, TEST AND DEFECTIVE WORK
12.1 Warranty G-55 12.2 Access to Work G-55 12.3 Test and Inspections G-55 12.4 Uncovering Work G-55 12.5 Owner May Stop the Work G-56 12.6 Pre-Completion Correction or Removal of Defective Work G-56 12.7 Post-Completion Correction Period G-56 12.8 Option to Accept Defective Work G-58 12.9 Owner May Correct Defective Work G-58
ARTICLE 13 - PAYMENTS TO CONTRACTOR AND COMPLETION
13.1 Schedule of Values G-59 13.2 Basis for Payments G-59 13.3 Stored Materials and Equipment G-59 13.4 Specially Manufactured Items G-59 13.5 Retainage G-60 13.6 Applications for Progress Payment G-60 13.7 Payment Reports G-61 13.8 Contractor's Warranty of Title G-61 13.9 Action Upon Application for Payment G-61 13.10 Substantial Completion G-62 13.11 Site Access Upon Substantial Completion G-62 13.12 Partial Utilization and Occupancy G-62 13.13 Final Inspection G-63 13.14 Final Application for Payment G-64 13.15 Final Payment and Acceptance G-64 13.16 Delayed Final Completion G-65 13.17 Contractor's Continuing Obligations G-65 13.18 Waiver of Claims by Final Payments G-65
ARTICLE 14 - SUSPENSION OF WORK AND TERMINATION
14.1 Owner May Suspend Work G-66 14.2 Contractor Default G-66 14.3 Default Termination by Owner G-66 14.4 Termination for Convenience G-68 14.5 Contractor Suspension of Work Right to Terminate G-69
ARTICLE 15 - DISPUTE RESOLUTION
15.2 Agreement to Arbitrate G-69 15.3 Claims Referred to Engineer G-69 15.4 Demand for Arbitration; Objection G-69 15.5 Consolidation and Joinder G-70 15.6 Enforcement of Award G-70
ARTICLE 16 - MISCELLANEOUS
16.1 Giving Notice G-70 16.2 Computation of Time G-70 16.3 Injury to Persons and Property G-71 16.4 Cumulative Duties and Rights G-71 16.5 Assignment G-71 16.6 Governing Law G-71 16.7 Salvage of Existing Equipment and Materials G-72 16.8 English Language Requirement G-72 16.9 Trade Practice G-72 16.10 Cross-References G-72 16.11 Accounting Records G-72 16.12 Steel Products G-72 16.13 Non-Discrimination G-72 16.14 Operating Instructions G-74 16.15 Operation and Maintenance Manual G-74 16.16 Service of Manufacturer's Representative G-75 16.17 Water G-76 16.18 Light and Power G-76 16.19 Prevention, Control and Abatement of Erosion and Water Pollution G-76 16.20 Air Borne Particulate G-77 16.21 Professional Fees and Court Costs Included G-77
Attachment A - Mediation Process G-78
|