ARTICLE 3 - CONTRACT DOCUMENTS

3.1 Integration of Contract Documents. The Contract Documents comprise the entire Agreement between OWNER and CONTRACTOR concerning the Work. The Contract Documents are complementary; what is called for by one is as binding as if called for by all. The Contract Documents will be construed in accordance with the law of the State of Indiana and without regard to the party by or for whom they were prepared or drafted.

3.2 Intent and Meaning. It is the intent of the Contract Documents to describe a functionally complete Project (or part thereof) to be constructed in accordance therewith. Any Work, materials or equipment that may reasonably be inferred from the Contract Documents as being required to produce the intended result will be supplied whether or not specifically called for. Notations, details or other descriptions which apply to one of a number of situations, materials, processes or work items shall apply to all except as specifically stated otherwise. When words which have a well-known technical or trade meaning are used to describe Work, materials or equipment, such words shall be given that meaning unless a different meaning is reasonably apparent as determined by the ENGINEER. Reference to standard specifications, manuals or codes of any technical society, organization or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual or code or Laws or Regulations in effect at the time of opening of Bids. If said standard specification, manual or code or Laws or Regulations are promulgated, amended, revised or otherwise changed subsequent to the opening of Bids, CONTRACTOR shall notify OWNER who may direct compliance under Section 9.1. However, no provision of any referenced standard specification, manual or code (whether or not specifically incorporated by reference in the Contract Documents) shall be effective to change the duties and responsibilities of OWNER, CONTRACTOR or ENGINEER, or any of their consultants, agents or employees, or to limit or impair any right or remedy of the OWNER, as set forth in the Contract Documents, nor shall it be effective to assign to the OWNER, ENGINEER or any of their respective consultants, agents or employees any duty or authority to supervise or direct the furnishing or performance of the Work or any duty or authority to undertake responsibility, contrary to the provisions of Section 8.10 or 8.11.

3.3 Duty To Report Discrepancies. If, during the performance of the Work, CONTRACTOR finds a conflict, error or discrepancy in the Contract Documents, CONTRACTOR shall so report to ENGINEER in writing at once and before proceeding with the Work affected thereby and shall obtain a written interpretation or clarification from ENGINEER.

3.4 Major Modifications. The Contract Documents may be amended to provide for additions, deletions and revisions in the Work or to modify the terms and conditions thereof by (i) a formal Written Amendment, or (ii) a Change Order (pursuant to Section 9.4) or (iii) a Work Directive Change (pursuant to Section 9.1). As indicated in Sections 10.2 and 11.5, the Contract Price and Contract Time may only be changed by a Change Order or a Written Amendment.

3.5 Minor Deviations. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized by (i) a Field Order (pursuant to Section 8.5), or (ii) an ENGINEER's approval of a Shop Drawing, Working Drawing, or samples (pursuant to Section 6.22) or an ENGINEER's written interpretation or clarification (pursuant to Section 8.4).

3.6 Reuse of Documents. Neither CONTRACTOR nor any Subcontractor or Supplier or other person or organization performing or furnishing any of the Work under a direct or indirect contract with OWNER shall have or acquire any title to or ownership rights in any of the Drawings, Specifications or other documents (or copies of any thereof) prepared by or bearing the seal of ENGINEER; and they shall not reuse any of them on extensions of the Project or any other project without written consent of OWNER and ENGINEER and specific written verification or adaptation by ENGINEER.

3.7 Any work, including the furnishing of materials, equipment, tools, labor, and incidentals required to carry out the terms of the Contract Documents shall be done by CONTRACTOR, its employees, or subcontractors unless specifically set out otherwise in the Contract Documents. The words "by the CONTRACTOR" or "the CONTRACTOR shall" will not necessarily be used to so indicate. All Work shall be carried out in a thorough, careful, effective and satisfactory manner without specifically using these words to describe the action.

 
 

Last Updated: 1/4/2007 |  Print This Page | Email to Friend

 

Home | Search | Services | Mayor | Council | City | County | Courts

© 1996 - 2008 All Rights Reserved | Privacy Statement | Terms of Use | About this Site